The project assumed reconstruction and extension of ul. Grygowa along with the construction of two viaducts and reconstruction of the switch to ul. Rataja and construction of the missing section of trolleybus traction in ul. Mełgiewska.In addition, the intersections of ul. Majdanek – Grabski – Sulisławicka Martyrs’ Road, intersection of ul. Majdanek – Aviation Martyrs’ Road and a key public transport interchange was constructed at the Lublin Roundabout July ’80 roundabout with inlets.The dynamic stop information system on the roads covered by the investment was expanded and rolling stock for trolleybus traction and bus lines was purchased.
Gallery
Details
Beneficiary
Gmina Lublin
Programme
The Operational Programme Eastern Poland
EU Fund
The European Regional Development Fund
Total project value
PLN 207,802,678.34
EU contribution
PLN 163,990,779.93